Approved and physically under way, or in force and being implemented.
Status: Under implementation. An approved decision is being carried out, often in phases.Roads and bridgesBronte Wyecroft Road extension and Bronte Creek bridge
Wyecroft Road west of Bronte Road, crossing Bronte Creek into Burlington · Led by Halton Region
A four-lane road and bridge linking Oakville and Burlington across Bronte Creek, carrying a new watermain, bike lanes and multi-use pathways.
- Project number
- PR-3303
- Construction started
- October 2023
- Anticipated completion
- Fall 2026
- Opening date
- Not yet published
- Roadway
- Four lanes
- Environmental assessment
- Completed 1994, addendum 2006
What happens next
Nov 2026
Lane restrictions end
Restrictions at Wyecroft Road and Bronte Road run to November 2026. Halton Region gives completion as fall 2026 and has not published an opening date.
Completion: Fall 2026, no opening date published
Status: Under implementation. An approved decision is being carried out, often in phases.Parks and public spaceOld Oakville Towne Square revitalization
Downtown Oakville, between Lakeshore Road East and Church Street · Led by Town of Oakville
A $7.5 million rebuild of the downtown square, phased over a year to keep businesses open.
- Project value
- $7.5 million
- Construction starts
- Week of 14 September 2026
- Completion
- September 2027
- George Street closure
- Lakeshore Road East to Church Street, from spring 2027
What happens next
Nov 2026
Phase 1 ends and work pauses for the holidays
Phased, with decorative hoarding and maintained access to businesses.
Completion: September 2027
What has changed
- 14 Sep 2026Construction began the week of 14 September. The Town lists Phase 1 as under way until November 2026.
Status: Under implementation. An approved decision is being carried out, often in phases.Roads and bridgesUptown Core Trafalgar Road widening, Hays Boulevard to Dundas Street
Trafalgar Road from Hays Boulevard to Dundas Street East, then on to William Halton Parkway · Led by Halton Region
Halton Region is widening Trafalgar Road from four lanes to six, with sidewalks, multi-use paths, a bike lane, new signals and a trunk wastewater main. The Hays to Dundas section has been under construction since March 2025.
- Project
- PR-2079D
- Contract 1
- Hays Blvd to Dundas St E, under construction
- Contract 2
- Dundas St E to William Halton Pkwy, in design; construction from 2027
- Construction started
- March 2025
- Lanes now
- Two each way, on a lane shift since December 2025
- Plaza entrance at 330–400 Dundas St E
- Closed December 2025 to November 2026
- Projected completion
- 2030
What happens next
Nov 2026
Plaza entrance from Trafalgar Road reopens
The Region gives the closure of the entrance to 330–400 Dundas Street East as running to November 2026.
Projected completion: 2030
Status: Under implementation. An approved decision is being carried out, often in phases.TransitMidtown Oakville Oakville GO Station expansion
Oakville GO Station, Cross Avenue, on the Lakeshore West line · Led by Metrolinx
Metrolinx is rebuilding Oakville GO, the busiest station on Lakeshore West, with a new accessible pedestrian bridge, rehabilitated platforms and a larger bus loop. Construction started in April 2026.
- Customers per day
- More than 10,270
- Construction contract
- Awarded April 2026
- Contractor
- Kenaidan Murphy Joint Venture
- Pedestrian bridge
- New, with four elevators and four staircases
- Bus loop
- Six more bus platforms
- Completion date
- Not published by Metrolinx
What happens next
Not scheduled
Platform work
Metrolinx lists the closure of Platform 1, a temporary widening of Platform 2 and a realigned pick-up and drop-off exit as upcoming, without dates. It has not published a completion date.
Completion: Not published
What has changed
- Apr 2026Metrolinx awarded the construction contract in early April and work began on site.
Status: Under implementation. An approved decision is being carried out, often in phases.Roads and bridgesBronte Burloak Drive underpass at the Lakeshore West rail line
Burloak Drive at the rail corridor, on the Oakville–Burlington boundary · Led by Metrolinx
Burloak Drive is being lowered under the Lakeshore West tracks so that road traffic no longer stops for trains. The new rail bridge went into service in June 2026; the road underneath is still being built.
- Partners
- Metrolinx, Town of Oakville, City of Burlington
- Contract awarded
- February 2022
- Project cost (2022)
- $177.3 million
- New rail bridge
- In service June 2026
- Road
- Room for six lanes, with bike lanes and multi-use paths
- Completion
- Town: "summer 2027" and "Q4 of 2027"; Metrolinx: not published
What happens next
Not scheduled
Underpass opens to traffic
Metrolinx lists the opening without a date. The Town's page gives two different completion dates, summer 2027 and the fourth quarter of 2027, and says closures of up to 30 days may still be needed.
Completion: 2027; the Town gives both summer and Q4
What has changed
- Jun 2026The new rail bridge went into service, after a closure of Burloak Drive from 22 May to 1 June.
Status: Under implementation. An approved decision is being carried out, often in phases.Roads and bridgesPalermo Dundas Street widening, Tremaine Road to Bronte Road
Dundas Street between Tremaine Road and Bronte Road, including the Tansley bridge over Bronte Creek · Led by Halton Region
Halton Region is widening Dundas Street from four lanes to six between Tremaine Road and Bronte Road, with new bridges, multi-use paths behind barriers and on-road bike lanes. Construction started in fall 2024.
- Project
- PR-2671B
- Construction started
- Fall 2024
- Lanes
- Four to six
- Includes
- New bridges, multi-use paths, bike lanes, bus shelters, signals
- Phase 1 completion
- 2027
What happens next
Not scheduled
Phase 1 completion
The Region gives 2027 without a month. Night work is required during construction.
Phase 1 completion: 2027
Status: Under implementation. An approved decision is being carried out, often in phases.Roads and bridgesGlenorchy Sixth Line widening, Threshing Mill Boulevard to William Halton Parkway
Sixth Line from Threshing Mill Boulevard north to William Halton Parkway, north Oakville · Led by Town of Oakville
The second phase of rebuilding Sixth Line from a two-lane rural road into a four-lane urban road with a centre median, bike lanes and parking lay-bys. Construction began in September 2025.
- Contractor
- Pacific Paving
- Construction began
- 22 September 2025
- From
- Two-lane rural road
- To
- Four lanes, centre median, on-road bike lanes
- Phase 1
- Dundas St to Threshing Mill Blvd, completed 2023
- Completion date
- Not published
What happens next
Not scheduled
Completion
The Town lists the work as continuing through 2026 and has not published a completion date.
Completion: Not published
Status: Under implementation. An approved decision is being carried out, often in phases.Water and wastewater
Trafalgar Road water and wastewater work, south Oakville
Trafalgar Road in south Oakville, with work areas at Cornwall Road and Argus Road · Led by Halton Region
Halton Region is replacing water and wastewater pipes under Trafalgar Road in south Oakville. Work started in June 2026 with permits and site set-up, and temporary closures of Trafalgar Road south of Cornwall Road and of Argus Road are planned.
- Project
- PR-3547
- Started
- June 2026
- Anticipated end
- December 2027
- Planned closures
- Argus Rd, and Trafalgar Rd south of Cornwall Rd; dates not yet published
- Traffic impact as of 17 August 2026
- None yet, per the Region
What happens next
Not scheduled
Road closures
The Region says it will publish closure dates before they start. None had been published when we checked.
Anticipated end: December 2027
Status: Under implementation. An approved decision is being carried out, often in phases.Health and care
Oakville Trafalgar Memorial Hospital expansion
Oakville Trafalgar Memorial Hospital, north Oakville · Led by Government of Ontario
A provincially funded fit-out of shelled space at the hospital, adding more than 110 inpatient beds. The Province marked the start of construction on 27 August 2026.
- Provincial investment
- More than $154 million
- Inpatient beds added
- More than 110
- Renovated space
- About 79,000 sq ft
- Operator
- Halton Healthcare
- Construction start marked
- 27 August 2026
What happens next
Not scheduled
Construction complete
The Province gives the end of 2027. It has not published a date for patients to use the new beds.
Construction complete: By the end of 2027
What has changed
- 27 Aug 2026The Province marked the start of construction.
Status: Under implementation. An approved decision is being carried out, often in phases.Health and care
The Village of Heritage Trails long-term care homes
Oakville, on surplus provincial land; the Province has not published the address · Led by Government of Ontario
Two 320-bed long-term care homes, 640 places in all, being built by Schlegel Villages on surplus provincial land. The Province marked the start of construction on 25 August 2026.
- Beds
- 640 in two homes
- New places
- 554
- Upgraded places
- 86
- Operator
- Schlegel Villages
- Construction start marked
- 25 August 2026
What happens next
Not scheduled
First residents
The Province expects the first residents in summer 2028.
First residents: Summer 2028
What has changed
- 25 Aug 2026The Province marked the start of construction.