Oakville development projects

What is being built, decided and finished in Oakville, and the next date anything can change.

Projects tracked
23
Under way now
10
Being decided
3
Recently completed
3

Town of Oakville, Halton Region and provincial sources; the latest check on 24 Sep.

Every entry is taken from a Town of Oakville, Halton Region or provincial source, and carries the date we last checked it against that source. Where a source does not state a figure or a date, the row is absent rather than estimated.

Every project at a glance

Oakville development projects tracked by OakvilleIQ, with type, lead agency, status, expected completion or next date, and the date last checked.
ProjectTypeLeadStatusExpected or nextChecked
Wyecroft Road extension and Bronte Creek bridgeRoads and bridgesHalton RegionUnder implementationCompletion: Fall 2026, no opening date published23 Sep
Towne Square revitalizationParks and public spaceTown of OakvilleUnder implementationCompletion: September 202724 Sep
Trafalgar Road widening, Hays Boulevard to Dundas StreetRoads and bridgesHalton RegionUnder implementationProjected completion: 203024 Sep
Oakville GO Station expansionTransitMetrolinxUnder implementationCompletion: Not published24 Sep
Burloak Drive underpass at the Lakeshore West rail lineRoads and bridgesMetrolinxUnder implementationCompletion: 2027; the Town gives both summer and Q424 Sep
Dundas Street widening, Tremaine Road to Bronte RoadRoads and bridgesHalton RegionUnder implementationPhase 1 completion: 202724 Sep
Sixth Line widening, Threshing Mill Boulevard to William Halton ParkwayRoads and bridgesTown of OakvilleUnder implementationCompletion: Not published24 Sep
Trafalgar Road water and wastewater work, south OakvilleWater and wastewaterHalton RegionUnder implementationAnticipated end: December 202724 Sep
Oakville Trafalgar Memorial Hospital expansionHealth and careGovernment of OntarioUnder implementationConstruction complete: By the end of 202724 Sep
The Village of Heritage Trails long-term care homesHealth and careGovernment of OntarioUnder implementationFirst residents: Summer 202824 Sep
Lakeshore Road East multi-use path, Allan Street to Winston ChurchillRoads and bridgesTown of OakvilleUnder reviewNo date published24 Sep
Provincial science facility, William Halton ParkwayPlanning rulesTown of OakvilleUnder reviewNo date published24 Sep
Westerkirk, Trafalgar Road and Burnhamthorpe Road EastHousing proposalsTown of OakvilleOpen for commentNo date published24 Sep
Dundas Urban Core building types and minimum heightPlanning rulesTown of OakvilleApprovedNo date published6 Sep
2172 Wyecroft Road, beside Bronte GOHousing proposalsTown of OakvilleApprovedNo date published24 Sep
Midtown Oakville Transit-Oriented CommunityHousing proposalsProvince of OntarioApprovedNo date published24 Sep
Data centre interim control by-lawPlanning rulesTown of OakvilleApprovedLast day to appeal: 1 Oct5 Sep
McCraney Creek bridge replacement on Lakeshore Road WestRoads and bridgesTown of OakvilleApprovedConstruction: Spring to end of 202724 Sep
New Central Library, 193 Church StreetCommunity facilitiesTown of OakvilleApprovedOpening: 2030, per the library board24 Sep
Kerr Street underpass at the Lakeshore West rail lineRoads and bridgesMetrolinxPausedRestart: Not scheduled24 Sep
William Halton Parkway extensionRoads and bridgesHalton RegionCompleteNo date published24 Sep
Sixteen Mile community centre, library and poolCommunity facilitiesTown of OakvilleCompleteNo date published24 Sep
Meadowridge ParkParks and public spaceTown of OakvilleCompleteNo date published24 Sep
Homes in the tracked pipeline

The tracked projects for which the Town has published a home count. Each bar keeps the Town's own wording, because an approximate figure charted as an exact one is a claim nobody made.

Homes in the tracked pipeline
CategoryHomes
Midtown Oakville Transit-Oriented Community, Four sites on Cross AvenueMore than 6,800
Westerkirk, Southeast corner of Trafalgar Road and Burnhamthorpe Road East6,420
2172 Wyecroft Road, South side of Wyecroft RoadAbout 1,191

3 of the 23 tracked items state a home count. The others are public works or policy measures, which do not have one.


Under construction or being carried out 10

Approved and physically under way, or in force and being implemented.

Status: Under implementation. An approved decision is being carried out, often in phases.Roads and bridgesBronte

Wyecroft Road extension and Bronte Creek bridge

Wyecroft Road west of Bronte Road, crossing Bronte Creek into Burlington · Led by Halton Region

A four-lane road and bridge linking Oakville and Burlington across Bronte Creek, carrying a new watermain, bike lanes and multi-use pathways.

Project number
PR-3303
Construction started
October 2023
Anticipated completion
Fall 2026
Opening date
Not yet published
Roadway
Four lanes
Environmental assessment
Completed 1994, addendum 2006

What happens next

Nov 2026

Lane restrictions end

Restrictions at Wyecroft Road and Bronte Road run to November 2026. Halton Region gives completion as fall 2026 and has not published an opening date.

Completion: Fall 2026, no opening date published

Status: Under implementation. An approved decision is being carried out, often in phases.Parks and public spaceOld Oakville

Towne Square revitalization

Downtown Oakville, between Lakeshore Road East and Church Street · Led by Town of Oakville

A $7.5 million rebuild of the downtown square, phased over a year to keep businesses open.

Project value
$7.5 million
Construction starts
Week of 14 September 2026
Completion
September 2027
George Street closure
Lakeshore Road East to Church Street, from spring 2027

What happens next

Nov 2026

Phase 1 ends and work pauses for the holidays

Phased, with decorative hoarding and maintained access to businesses.

Completion: September 2027

What has changed
  1. 14 Sep 2026Construction began the week of 14 September. The Town lists Phase 1 as under way until November 2026.
Status: Under implementation. An approved decision is being carried out, often in phases.Roads and bridgesUptown Core

Trafalgar Road widening, Hays Boulevard to Dundas Street

Trafalgar Road from Hays Boulevard to Dundas Street East, then on to William Halton Parkway · Led by Halton Region

Halton Region is widening Trafalgar Road from four lanes to six, with sidewalks, multi-use paths, a bike lane, new signals and a trunk wastewater main. The Hays to Dundas section has been under construction since March 2025.

Project
PR-2079D
Contract 1
Hays Blvd to Dundas St E, under construction
Contract 2
Dundas St E to William Halton Pkwy, in design; construction from 2027
Construction started
March 2025
Lanes now
Two each way, on a lane shift since December 2025
Plaza entrance at 330–400 Dundas St E
Closed December 2025 to November 2026
Projected completion
2030

What happens next

Nov 2026

Plaza entrance from Trafalgar Road reopens

The Region gives the closure of the entrance to 330–400 Dundas Street East as running to November 2026.

Projected completion: 2030

Source: Halton Region

Last checked 24 Sep

Status: Under implementation. An approved decision is being carried out, often in phases.TransitMidtown Oakville

Oakville GO Station expansion

Oakville GO Station, Cross Avenue, on the Lakeshore West line · Led by Metrolinx

Metrolinx is rebuilding Oakville GO, the busiest station on Lakeshore West, with a new accessible pedestrian bridge, rehabilitated platforms and a larger bus loop. Construction started in April 2026.

Customers per day
More than 10,270
Construction contract
Awarded April 2026
Contractor
Kenaidan Murphy Joint Venture
Pedestrian bridge
New, with four elevators and four staircases
Bus loop
Six more bus platforms
Completion date
Not published by Metrolinx

What happens next

Not scheduled

Platform work

Metrolinx lists the closure of Platform 1, a temporary widening of Platform 2 and a realigned pick-up and drop-off exit as upcoming, without dates. It has not published a completion date.

Completion: Not published

What has changed
  1. Apr 2026Metrolinx awarded the construction contract in early April and work began on site.

Source: Metrolinx, Metrolinx

Last checked 24 Sep

Status: Under implementation. An approved decision is being carried out, often in phases.Roads and bridgesBronte

Burloak Drive underpass at the Lakeshore West rail line

Burloak Drive at the rail corridor, on the Oakville–Burlington boundary · Led by Metrolinx

Burloak Drive is being lowered under the Lakeshore West tracks so that road traffic no longer stops for trains. The new rail bridge went into service in June 2026; the road underneath is still being built.

Partners
Metrolinx, Town of Oakville, City of Burlington
Contract awarded
February 2022
Project cost (2022)
$177.3 million
New rail bridge
In service June 2026
Road
Room for six lanes, with bike lanes and multi-use paths
Completion
Town: "summer 2027" and "Q4 of 2027"; Metrolinx: not published

What happens next

Not scheduled

Underpass opens to traffic

Metrolinx lists the opening without a date. The Town's page gives two different completion dates, summer 2027 and the fourth quarter of 2027, and says closures of up to 30 days may still be needed.

Completion: 2027; the Town gives both summer and Q4

What has changed
  1. Jun 2026The new rail bridge went into service, after a closure of Burloak Drive from 22 May to 1 June.

Source: Town of Oakville, Metrolinx

Last checked 24 Sep

Status: Under implementation. An approved decision is being carried out, often in phases.Roads and bridgesPalermo

Dundas Street widening, Tremaine Road to Bronte Road

Dundas Street between Tremaine Road and Bronte Road, including the Tansley bridge over Bronte Creek · Led by Halton Region

Halton Region is widening Dundas Street from four lanes to six between Tremaine Road and Bronte Road, with new bridges, multi-use paths behind barriers and on-road bike lanes. Construction started in fall 2024.

Project
PR-2671B
Construction started
Fall 2024
Lanes
Four to six
Includes
New bridges, multi-use paths, bike lanes, bus shelters, signals
Phase 1 completion
2027

What happens next

Not scheduled

Phase 1 completion

The Region gives 2027 without a month. Night work is required during construction.

Phase 1 completion: 2027

Source: Halton Region

Last checked 24 Sep

Status: Under implementation. An approved decision is being carried out, often in phases.Roads and bridgesGlenorchy

Sixth Line widening, Threshing Mill Boulevard to William Halton Parkway

Sixth Line from Threshing Mill Boulevard north to William Halton Parkway, north Oakville · Led by Town of Oakville

The second phase of rebuilding Sixth Line from a two-lane rural road into a four-lane urban road with a centre median, bike lanes and parking lay-bys. Construction began in September 2025.

Contractor
Pacific Paving
Construction began
22 September 2025
From
Two-lane rural road
To
Four lanes, centre median, on-road bike lanes
Phase 1
Dundas St to Threshing Mill Blvd, completed 2023
Completion date
Not published

What happens next

Not scheduled

Completion

The Town lists the work as continuing through 2026 and has not published a completion date.

Completion: Not published

Source: Town of Oakville

Last checked 24 Sep

Status: Under implementation. An approved decision is being carried out, often in phases.Water and wastewater

Trafalgar Road water and wastewater work, south Oakville

Trafalgar Road in south Oakville, with work areas at Cornwall Road and Argus Road · Led by Halton Region

Halton Region is replacing water and wastewater pipes under Trafalgar Road in south Oakville. Work started in June 2026 with permits and site set-up, and temporary closures of Trafalgar Road south of Cornwall Road and of Argus Road are planned.

Project
PR-3547
Started
June 2026
Anticipated end
December 2027
Planned closures
Argus Rd, and Trafalgar Rd south of Cornwall Rd; dates not yet published
Traffic impact as of 17 August 2026
None yet, per the Region

What happens next

Not scheduled

Road closures

The Region says it will publish closure dates before they start. None had been published when we checked.

Anticipated end: December 2027

Source: Halton Region

Last checked 24 Sep

Status: Under implementation. An approved decision is being carried out, often in phases.Health and care

Oakville Trafalgar Memorial Hospital expansion

Oakville Trafalgar Memorial Hospital, north Oakville · Led by Government of Ontario

A provincially funded fit-out of shelled space at the hospital, adding more than 110 inpatient beds. The Province marked the start of construction on 27 August 2026.

Provincial investment
More than $154 million
Inpatient beds added
More than 110
Renovated space
About 79,000 sq ft
Operator
Halton Healthcare
Construction start marked
27 August 2026

What happens next

Not scheduled

Construction complete

The Province gives the end of 2027. It has not published a date for patients to use the new beds.

Construction complete: By the end of 2027

What has changed
  1. 27 Aug 2026The Province marked the start of construction.

Source: Government of Ontario

Last checked 24 Sep

Status: Under implementation. An approved decision is being carried out, often in phases.Health and care

The Village of Heritage Trails long-term care homes

Oakville, on surplus provincial land; the Province has not published the address · Led by Government of Ontario

Two 320-bed long-term care homes, 640 places in all, being built by Schlegel Villages on surplus provincial land. The Province marked the start of construction on 25 August 2026.

Beds
640 in two homes
New places
554
Upgraded places
86
Operator
Schlegel Villages
Construction start marked
25 August 2026

What happens next

Not scheduled

First residents

The Province expects the first residents in summer 2028.

First residents: Summer 2028

What has changed
  1. 25 Aug 2026The Province marked the start of construction.

Source: Government of Ontario

Last checked 24 Sep


Being decided 3

An application, study or review that has not reached a decision.

Status: Under review. A public body is actively considering it. Options may not exist yet.Roads and bridgesOld OakvilleSoutheast Oakville

Lakeshore Road East multi-use path, Allan Street to Winston Churchill

Lakeshore Road East from Allan Street to Winston Churchill Boulevard · Led by Town of Oakville

The Town studied cycling on Lakeshore Road East and now prefers a continuous multi-use path, because provincial Bill 60 limits taking away vehicle lanes for bike lanes. Public feedback closed on 24 July 2026.

Preferred option
Continuous multi-use path
Ruled out
On-road bike lanes, because of Bill 60
Public information centre
23 June 2026
Feedback closed
24 July 2026
Construction
Not scheduled

What happens next

Not scheduled

Recommendation

The Town has not published when a recommendation or design will come forward.

Source: Town of Oakville

Last checked 24 Sep

Status: Under review. A public body is actively considering it. Options may not exist yet.Planning rules

Provincial science facility, William Halton Parkway

North side of William Halton Parkway, east of Hospital Gate, ward 7 · Led by Town of Oakville

Infrastructure Ontario has applied for a four-storey provincial laboratory and regulatory complex, and a new public road linking Glenorchy Road to Hospital Gate. The statutory public meeting was held on 7 July 2026.

Applicant
Infrastructure Ontario
Files
OPA1326.06, Z.1326.06, 24T-26003/1326
Building
Four storeys, where the plan requires at least six
Use
Environmental and radiological laboratories, monitoring and enforcement
Statutory public meeting
7 July 2026

What happens next

Not scheduled

Recommendation report

No recommendation meeting has been noticed.

Source: Town of Oakville

Last checked 24 Sep

Status: Open for comment. A consultation, public meeting or appeal window is open now.Housing proposals

Westerkirk, Trafalgar Road and Burnhamthorpe Road East

Southeast corner of Trafalgar Road and Burnhamthorpe Road East · Led by Town of Oakville

An official plan amendment, rezoning and draft plan of subdivision for 6,420 homes across 27 buildings in seven phases.

Applicant
1816986 Ontario Inc. (Westerkirk)
Files
OPA1312.14, Z.1312.14, 24T-26002/1312
Ward
7
Homes
6,420
Buildings
27, from 3 to 30 storeys
Towers
10, from 18 to 30 storeys
Commercial space
14,475 m²
Parking spaces
7,703

What happens next

Not scheduled

Staff recommendation report

The statutory public meeting was held on 8 September 2026; the Town's notice says no recommendation to approve or refuse is made at that meeting. The next step is a staff report to the Planning and Development Council, for which no date is published.


Decided 6

A decision has been taken. Construction, where there is any, has not started.

Status: Approved. A decision has been taken. It has not necessarily taken effect.Planning rulesGlenorchyPalermoJoshua Creek

Dundas Urban Core building types and minimum height

Lands north of Dundas Street in the Dundas Urban Core area, wards 6 and 7 · Led by Town of Oakville

A Town-initiated amendment permitting only apartment, mixed-use and commercial buildings within 50 metres of Dundas Street, with a six-storey minimum where there are homes.

Adopting by-law
2026-105
Official plan amendment
341
Zoning amendment
2026-106
File
42.15.74
Wards
6 and 7
Area affected
Within 50 m of the Dundas right of way
Minimum height where residential
Six storeys

What happens next

Not scheduled

Next step

The appeal window closed on 6 August 2026. The amendment now applies to new applications on the affected lands; no further Town date is published.

Status: Approved. A decision has been taken. It has not necessarily taken effect.Housing proposalsBronte

2172 Wyecroft Road, beside Bronte GO

South side of Wyecroft Road, west of Third Line, adjacent to Bronte GO Station · Led by Town of Oakville

Rezoned from industrial to urban core mixed use for four towers, about 1,191 homes, retail and a daycare.

Applicant
NBIM 2172 Wyecroft LP
File
Z.1627.02
Ward
1
Homes
About 1,191
Towers
Four, at 21 and 24 storeys
Retail and commercial
2,550 m²
Daycare
1,355 m²
Density
4.78 FSI

What happens next

Not scheduled

Holding provisions to be lifted

The appeal period closed on 9 September 2026. Whether an appeal was filed is not published by the Town; the Ontario Land Tribunal's case search is the place to check. If none was, the holding provisions must be satisfied before the permissions take effect, and no date is published for that.

Status: Approved. A decision has been taken. It has not necessarily taken effect.Housing proposalsMidtown Oakville

Midtown Oakville Transit-Oriented Community

Four sites on Cross Avenue, Argus Road and South Service Road East, around Oakville GO · Led by Province of Ontario

Four Minister's Zoning Orders permitting 11 buildings across four sites. They override municipal zoning and cannot be appealed.

Sites
Four
Buildings
11
Homes
More than 6,800
Height as issued
Up to 56 storeys
Height the Province has committed to
38 storeys
Appeal rights
None under the Planning Act

What happens next

Not scheduled

Decision on Official Plan Amendment 70

The Town's own framework for Midtown has been with the Minister of Municipal Affairs and Housing since February 2025. No decision date has been published.

Status: Approved. A decision has been taken. It has not necessarily taken effect.Planning rulesSoutheast Oakville

Data centre interim control by-law

All employment and Parkway Belt West designations, wards 1 to 7 · Led by Town of Oakville

A one-year freeze on data centre applications across the town's employment land, while staff study how to regulate them.

By-law
2026-129
Authority
Planning Act, section 38
Passed
11 August 2026
In effect until
11 August 2027
Wards affected
1 to 7

What happens next

Awaiting an update

Last day to appeal was scheduled for 1 Oct. The source has not yet published what follows.

Status: Approved. A decision has been taken. It has not necessarily taken effect.Roads and bridges

McCraney Creek bridge replacement on Lakeshore Road West

Lakeshore Road West near 602 Lakeshore Road West, close to Fourth Line · Led by Town of Oakville

The Town will replace and enlarge the McCraney Creek crossing under Lakeshore Road West. Construction needs a full closure of Lakeshore Road for up to 60 days, and lane reductions for utility work start this fall.

Road closure
Lakeshore Road West, up to 60 days
Utility relocations
Fall 2026 into 2027, with lane reductions
Detailed design complete
December 2026
Tender
February 2027
Construction
Spring 2027 to end of 2027

What happens next

Dec 2026

Detailed design complete

Then a tender in February 2027. The Town has not yet published the dates of the Lakeshore Road closure.

Construction: Spring to end of 2027

Source: Town of Oakville

Last checked 24 Sep

Status: Approved. A decision has been taken. It has not necessarily taken effect.Community facilitiesOld Oakville

New Central Library, 193 Church Street

193 Church Street, the former post office, downtown Oakville · Led by Town of Oakville

The central library is moving from Navy Street to the former post office at 193 Church Street as part of the Downtown Cultural Hub. Council funded construction in the 2026 budget and chose to keep part of the building's facade.

Construction funding
Approved in the 2026 budget, December 2025
Design option
Partial facade retained, approved February 2026
Moving from
120 Navy Street
Opening
2030 (Oakville Public Library)
Construction start
Not published

What happens next

Not scheduled

Construction start

Neither the Town nor the library board has published a construction start date.

Opening: 2030, per the library board

What has changed
  1. Feb 2026Council chose to proceed with a partial facade retained.
  2. Dec 2025Council approved construction funding in the 2026 budget.

Source: Town of Oakville, Oakville Public Library

Last checked 24 Sep


Paused 1

Suspended, and able to resume without a new decision.

Status: Paused. Suspended. It can resume without a new decision.Roads and bridges

Kerr Street underpass at the Lakeshore West rail line

Kerr Street at the Lakeshore West rail corridor · Led by Metrolinx

An underpass to widen Kerr Street under the tracks, with turn lanes, sidewalks and bike lanes. Metrolinx deferred it indefinitely in February 2022 after the estimated cost rose from $130 million to $234 million.

Deferred
24 February 2022
2016 estimate
$130 million
2022 estimate
$234 million
Oakville's share at the 2016 estimate
$65 million
Restart date
Not published

What happens next

Not scheduled

Restart

The Town says staff are working with Metrolinx on a way to restart the project. No date has been published.

Restart: Not scheduled

Source: Town of Oakville

Last checked 24 Sep


Recently completed 3

Finished and in use.

Status: Complete. Finished. The change is fully in effect and nothing further is scheduled.Roads and bridgesGlenorchyPalermo

William Halton Parkway extension

Between Neyagawa Boulevard and Harasym Trail, crossing Sixteen Mile Creek · Led by Halton Region

The bridge over Sixteen Mile Creek and its connecting roadway, completing about 12 kilometres of continuous route between Ninth Line and Bronte Road.

Opened
August 2026
Corridor length
About 12 km
Runs between
Ninth Line and Bronte Road
Roundabouts
Four
Funding approved
2019

What happens next

Not scheduled

Finishing work

Landscaping, fencing and signage continue, with possible short-term lane restrictions. Halton Region has published no date for their completion.

What has changed
  1. 21 Aug 2026Opened to traffic between Neyagawa Boulevard and Harasym Trail.
Status: Complete. Finished. The change is fully in effect and nothing further is scheduled.Community facilities

Sixteen Mile community centre, library and pool

Sixteen Mile Sports Complex, 3070 Neyagawa Boulevard · Led by Town of Oakville

The expansion of the Sixteen Mile Sports Complex into a community centre, with a new branch library and an aquatic centre. The community centre and library opened on 31 March 2026 and the pool on 20 July 2026.

Community centre
About 65,000 sq ft, opened 31 March 2026
Library branch
More than 18,000 sq ft, opened 31 March 2026
Aquatic centre
Opened 20 July 2026

What happens next

Not scheduled

Nothing scheduled

The community centre, library and pool are all open.

What has changed
  1. 20 Jul 2026The aquatic centre opened.
  2. 31 Mar 2026The community centre and Sixteen Mile library branch opened.

Source: Town of Oakville, Town of Oakville

Last checked 24 Sep

Status: Complete. Finished. The change is fully in effect and nothing further is scheduled.Parks and public space

Meadowridge Park

3160 Meadowridge Drive · Led by Town of Oakville

A 4.4-hectare Town park at 3160 Meadowridge Drive. The Town reports construction complete and the park open as of July 2026.

Size
4.4 hectares
Opened
July 2026

What happens next

Not scheduled

Nothing scheduled

The park is open. The Town lists no further work on it.

What has changed
  1. Jul 2026Construction complete and the park open, per the Town.

Source: Town of Oakville

Last checked 24 Sep


What this tracker covers, and what it leaves out

It covers the projects a resident is most likely to notice or be affected by: new roads and bridges, community facilities, major public works, and the planning decisions that set how much can be built and where. An entry is added only when a public body has published a status and, for anything physical, a timeframe.

It does not reproduce the Town’s full list of active development applications. Those listings give an address, an applicant and a file number, and nothing else: no status, no unit count, no dates. Filling those columns by inference is exactly what this tracker exists to avoid. The ward listings are linked from every area page, and the source pages we watch are on our monitored source list.

Short-term road closures are not tracked here. The Town and the Region publish those daily, and a copy would be out of date within hours.