Major road projects in Oakville

Multi-year road, bridge and rail-crossing projects, with timelines as the Town and Region state them.

Summary

Halton Region opened the Wyecroft Road extension and bridge between Bronte Road and Burloak Drive on November 20, 2026, and projects its Trafalgar Road widening north of Hays Boulevard to finish in 2030. The Town lists the Burloak Drive rail underpass for completion in 2027 and the Speers Road widening for 2028. Every timeline here is as its project owner stated it on November 26, 2026.

Last verified

Administered by the road owners: Halton Region for Regional roads such as Trafalgar Road and the new Wyecroft Road extension, and the Town of Oakville for Town roads and, with the City of Burlington and Metrolinx, the Burloak Drive rail underpass. Every answer below was checked against its source on November 26, 2026; the source is linked under each one.

Halton Region projects

Is the Wyecroft Road extension and bridge open?

Yes. Halton Region opened the extension of Wyecroft Road between Bronte Road and Burloak Drive, including the new bridge, on November 20, 2026; the project also includes a new watermain to support water supply to Oakville. The Region's project page lists the status as complete, but says intermittent construction work may continue and lane restrictions may be put in place, and asks drivers to plan ahead and take care in the area.

Source: Halton Region, Wyecroft Road Extension and Bridge Project

What is happening on Trafalgar Road, and how long will it last?

Halton Region has finished phase 1, between Leighland Avenue and north of Hays Boulevard. Phase 2, from Hays Boulevard to William Halton Parkway, widens the road from four to six lanes, with new sidewalks and multi-use pathways, a bike lane, a bus bay, lighting, traffic signals, a culvert replacement and a new trunk wastewater main. Its first contract, Hays Boulevard to Dundas Street East, began construction in March 2025; the second, Dundas Street East to William Halton Parkway, is in design with construction anticipated to start in 2027. The Region's tentative projected completion is 2030.

Source: Halton Region, Trafalgar Road Improvements

How is Trafalgar Road construction affecting traffic now?

From November 2026, traffic on Trafalgar Road between Hays Boulevard and Dundas Street East is shifted to the east side of the road, with two lanes open in each direction. Planned night work runs from 7 p.m. to 7 a.m., weather permitting. Oak Walk Drive, between Trafalgar Road and Taunton Road, remains closed until December 2, 2026, with traffic detoured by Taunton Road and Hays Boulevard. Emergency, business and local access is maintained at all times.

Source: Halton Region, Trafalgar Road Improvements

Town of Oakville projects

When will the Burloak Drive rail underpass be finished?

The Town's project page gives two dates: its overview says the project is scheduled to be completed in Q4 of 2027, and its timeline says construction completion is anticipated in summer 2027. The underpass, a joint project of the Town of Oakville, the City of Burlington and Metrolinx, separates road traffic on Burloak Drive from the rail line and adds turn lanes, sidewalks, bike lanes and better active transportation connections. A four-lane detour road keeps Burloak Drive open in place of the 14-month closure first planned; the page says further closures of up to 30 days will be needed to shift traffic onto the widened road, and periodic lane closures can happen at any time.

Source: Town of Oakville, Burloak Drive Grade Separation

When will the Speers Road widening be done?

The Town is widening Speers Road to five lanes from Fourth Line to Dorval Drive, as phase two of the project, with active transportation improvements, watermain replacement and wastewater upgrades. Hydro and utility relocation began in summer 2024; the Town's page says construction will begin in spring 2026, with anticipated completion in 2028. The speed limit is reduced to 50 km/h within the project limits, and new traffic signals are planned at Fourth Line, 447 Speers Road and Morden Road.

Source: Town of Oakville, Speers Road Widening

What is happening on Sixth Line?

The Town is rebuilding Sixth Line from a two-lane rural road into an urbanized four-lane road with a centre median, on-road bike lanes, parking lay-bys and landscaping. Phase one, Dundas Street to Threshing Mill Boulevard, was completed in 2023. For phase two, Threshing Mill Boulevard to William Halton Parkway, utility relocations finished in 2023 and underground work in spring 2024, and the Town's page says road work was set to begin September 22, 2025. The page gives no completion date and lists lane closures and shifting traffic lanes among the expected impacts.

Source: Town of Oakville, Sixth Line Widening

Is Wyecroft Road being widened between Bronte Road and Third Line?

Yes, but construction is years away. The Town's project, following a 2018 environmental assessment, widens Wyecroft Road from Bronte Road to Third Line for walking, cycling, transit and driving, now with off-road cycle tracks. Its timeline lists detailed design from 2025 to 2027, property acquisition from 2026 to 2027, Halton's Burloak and Wyecroft watermain construction from 2027 to 2028, utility relocations from 2028 to 2029, and road construction beginning in 2029 to 2030.

Source: Town of Oakville, Wyecroft Road Widening and Active Transportation - Bronte Road to Third Line

Will Lakeshore Road West close for the McCraney Creek culvert?

Yes, for up to 60 days. The Town is replacing and upsizing the McCraney Creek culvert on Lakeshore Road, near 602 Lakeshore Road West, and traffic will be moved to a detour during culvert construction. Detailed design is to be complete in December 2026, with tendering in February 2027; tree clearing and utility relocations, with reduced lanes, are expected from fall 2026 into 2027; and culvert construction and road resurfacing are planned from spring 2027 to the end of 2027.

Source: Town of Oakville, McCraney Creek Bridge Replacement

What happened to the Kerr Street rail underpass?

Metrolinx has indefinitely deferred the Kerr Street grade separation, an underpass at the Lakeshore West GO line that was also to add turn lanes, sidewalks, bike lanes and a lane in each direction. The Town learned of the deferral and a higher cost on February 24, 2022: estimated at $130 million in 2016, with Oakville's share $65 million, the cost had risen to $234 million. The Town says Council remains committed to exploring all options to fund and resume the project, and staff are working with Metrolinx on a way to restart it.

Source: Town of Oakville, Kerr Street Grade Separation

Sources

Every factual claim above traces to one of these documents.
  1. Halton Region

    Wyecroft Road Extension and Bridge Project

    Retrieved November 26, 2026

  2. Halton Region

    Trafalgar Road Improvements

    Retrieved November 26, 2026

  3. Town of Oakville

    Burloak Drive Grade Separation

    Retrieved November 26, 2026

  4. Town of Oakville

    Speers Road Widening

    Retrieved November 26, 2026

  5. Town of Oakville

    Sixth Line Widening

    Retrieved November 26, 2026

  6. Town of Oakville

    McCraney Creek Bridge Replacement

    Retrieved November 26, 2026

  7. Town of Oakville

    Kerr Street Grade Separation

    Retrieved November 26, 2026