Wyecroft Road extension and Bronte Creek bridge to Burlington open Friday evening, Halton Region says
Halton Region held the official opening of the Wyecroft Road Extension and Bridge on November 20, 2026 and said the four-lane crossing between Bronte Road and Burloak Drive would open to the public that evening, around 6 p.m.
In this story
The details
When it opens
Halton Region announced the official opening of the Wyecroft Road Extension and Bridge on Friday, November 20, 2026. In a media release that day, the Region said the road and bridge would open to the public after 6 p.m. The Region's project page, updated the same day, says the extension and the new bridge over Bronte Creek will be open to traffic by 6 p.m. on Friday, November 20, 2026.
The new road connects Wyecroft Road between Bronte Road and Burloak Drive. The Region describes it as a new connection between the Town of Oakville and the City of Burlington across Bronte Creek and a new east-west route for residents, businesses and visitors.
What drivers should expect
The opening does not mean all work has ended. The project page says that after the road opens, intermittent construction work may continue and lane restrictions may be implemented. The Region asks people to plan ahead and exercise caution when travelling through the area.
What was built
- Friday, November 20, 2026, around 6 p.m.
- Wyecroft Road between Bronte Road and Burloak Drive
- Bronte Creek, between Oakville and Burlington
- Four lanes
- Multi-use pathways, on-road bike lanes and a new watermain
- $63.9 million
- $53.1 million
- October 2023
- PR-3303
- Complete
The release says the project was made possible through funding of $63.9 million from Halton Region and $53.1 million from the Provincial Government. The new watermain, it says, will help support future growth and the delivery of water services in Oakville.
What the Region says it changes
- An additional route between Oakville and Burlington.
- Help alleviating pressure on local roads and the QEW.
- Reduced travel times to Appleby and Bronte GO stations.
- Improved access to employment lands, businesses and retail areas.
- New and safer opportunities for walking and cycling.
Those are the benefits the Region lists in its release for motorists, pedestrians, cyclists, transit users and first responders. The release does not give traffic forecasts or travel-time figures.
By creating a new connection across Bronte Creek, this project enhances mobility, improves access to key destinations and supports the safe and efficient movement of people throughout Halton.
How long it took
The project page gives a construction start of October 2023 and lists project funding for the extension and bridge crossings as approved in 2019. It says the Town of Oakville completed the environmental assessment study for the project in 1994 and issued an addendum in 2006.
Sources
Halton Region
Wyecroft Road Extension and Bridge Project