Status: Under appeal. A decision, or the lack of one, has been appealed to the Ontario Land Tribunal.
Development application
Distrikt Developments
Distrikt Developments (157 Cross Ave) is an application for 1,198 homes in Midtown Core, Ward 3, filed as plan of subdivision, official plan amendment, zoning by-law amendment. It has been appealed to the Ontario Land Tribunal; the first application was received in 2024/03.
At a glance
Stage
Under appeal
Town status
Appealed
Address
157 Cross Ave. Oakville
Official Plan community
Midtown Core
Ward
3
Homes proposed
1,198
Residential land
0.96 ha
First application received
March 8, 2024
Last checked October 22, 2026·Town of Oakville·How we know
Contains information licensed under the Open Government Licence — Town of Oakville. Terms
From the source
application status · unit counts and floor areas · milestone dates · the description of the proposal
Derived by OakvilleIQ
the stage label · grouping of folders into one project · community and ward by the site's location · what is nearby
OakvilleIQ’s words
the summary sentence
Kept current
Rebuilt from the Town's layer; a weekly check warns when the record is more than 90 days old.
At a glance
Stage
Under appeal
Town status
Appealed
Address
157 Cross Ave. Oakville
Official Plan community
Midtown Core
Ward
3
Homes proposed
1,198
Residential land
0.96 ha
First application received
March 8, 2024
Imagery: Esri, Maxar, Earthstar Geographics
What is proposed
The proposal contemplates two, 46- and 61-storey towers above a shared 3-storey mixed-use podium base. An at-grade privately-owned publicly accessible space to be located at the southeast corner of the Subject Site with a pedestrian connection to the future east-west road to the north.
Previous Pre-consultation June 28, 2023
The Town’s description of the application, as recorded in its planning system.
Homes by type
Type
Proposed
Approved
Apartments
1,198
—
Total
1,198
—
What has happened
Every dated milestone in the Town’s record for this project’s applications, in order. Nothing is inferred between them.
March 8, 2024
Application received · Plan of subdivision, Official plan amendment, Zoning by-law amendment 24002/1614, 1614.83
March 14, 2024
Deemed complete · Zoning by-law amendment 1614.83
Awaiting an update. The Town’s record shows nothing dated after March 14, 2024; the next recorded step appears here when the Town enters it.
Contains information licensed under the Open Government Licence — Town of Oakville. Licence. Figures are the Town’s records at the date checked; a later submission can change them.