Construction starts on north Oakville's next Catholic elementary school, a 671-student building at 3500 Post Road

The Halton Catholic District School Board broke ground on November 3 on North Oakville #3 Catholic Elementary School, near Burnhamthorpe Road West and Sixth Line. The Province is paying $32.7 million; the board has not given an opening date.

OakvilleIQ Newsroom3 sources · 3 min read

Email
Aerial view of 3500 Post Road, Oakville
Imagery: Esri, Maxar, Earthstar Geographics

Where this is

Where 3500 Post Road is in Oakville3500 Post Road, with Oakville #5 PS, 3490 Preserve Drive shown for reference, on a map of the Town of Oakville and its Official Plan communities.3500 Post RoadOakville #5 PS, 3490 Preserve Drive
3500 Post RoadOakville #5 PS, 3490 Preserve Drive (reference)Outlines are the Town’s Official Plan communities.
In this story4 sections
  1. What happened
  2. The school
  3. Nearby: the HDSB's Oakville #5 PS
  4. What happens next

The details

What happened

The Halton Catholic District School Board held a groundbreaking and blessing ceremony on Tuesday, November 3, 2026 at the site of its new North Oakville #3 Catholic Elementary School, 3500 Post Road, near Burnhamthorpe Road West and Sixth Line. In a release the next day, the board said the ceremony marked the beginning of construction on a school meant to meet the needs of Oakville's growing Catholic school community.

Board Chair Marvin Duarte and Chief Executive Officer and Chief Education Officer John Klein attended, along with Mayor-elect Jeff Knoll, who is still the Ward 5 Town and Regional Councillor until the new term begins, and Ward 7 councillors Nav Nanda and Scott Xie. Reverend Jerry Punnassery of Mary Mother of God Catholic Church in Oakville blessed the site.

The school

North Oakville #3 Catholic Elementary School, as described by the board and the Town
Site
3500 Post Road, near Burnhamthorpe Road West and Sixth Line (Ward 7, Glenorchy)
Students
671 elementary pupil places
Child care
A five-room child care centre; 88 licensed spaces, according to the MPP
Provincial funding
$32.7 million, according to the MPP
Construction start marked
November 3, 2026
Opening date
Not published
Permanent name
Not announced; North Oakville #3 CES is the planning name
Town site plan file
1315.005/01, with plans submitted in March and July 2026

The board's release describes a three-storey building. The Town's public site plan file for the same address describes a two-storey elementary school with a child care centre to be run by a third-party provider. The board's school-planning page says it was approved for Ministry of Education capital funding through the 2024-25 Capital Priorities Program.

With $32.7 million in provincial funding, this new Catholic elementary school will create 671 student spaces and 88 licensed childcare spaces, giving local families greater access to quality education and childcare close to home.
Effie Triantafilopoulos, MPP for Oakville North-Burlington, in a statement quoted in the board's release

In the same statement, the MPP said the Province has approved six new schools and one school expansion in Oakville North-Burlington since 2018, creating 5,400 student spaces and 440 child-care spaces. That figure covers the whole riding, which includes part of Burlington, not Oakville alone.

Nearby: the HDSB's Oakville #5 PS

Less than a kilometre to the south, by the Town planning layer's coordinates for the two sites, is the Halton District School Board's Oakville #5 Public School at 3490 Preserve Drive, which broke ground on September 10 and which that board expects to open in fall 2028 with 926 student places and 88 licensed child-care spaces. The two projects together add close to 1,600 elementary places in one corner of Glenorchy.

What happens next

Where North Oakville #3 CES stands
  1. Done: Provincial funding

    Approved through the 2024-25 Capital Priorities Program.

  2. Done: Site plan

    Plans filed with the Town in March 2026 and resubmitted in July 2026.

  3. Done: Groundbreaking

    Ceremony and blessing on November 3, 2026.

  4. Now: Construction

    Under way; the board says it will post construction reports monthly on its school-planning page.

  5. Next: Name and attendance area

    Not yet announced.

  6. Next: Opening

    No date published.

For families, the questions that matter most, which streets the school will serve and when it opens, have not been answered yet. The board sets attendance areas through its own boundary review process, and has published neither an opening year nor a name for the school.

Sources

Every factual claim above traces to one of these documents.

  1. Halton Catholic District School Board

    HCDSB Celebrates Groundbreaking and Blessing of New North Oakville #3 Catholic Elementary School

    Published November 4, 2026 · Retrieved November 5, 2026

  2. Halton Catholic District School Board

    North Oakville #3 Catholic Elementary School

    Retrieved November 5, 2026

Spotted an error? We keep the URL, update the timestamp and record the change. Our corrections policy.