Towne Square work to pause from mid-December, with fencing and equipment removed for the holidays

The Town says crews found unexpected conditions that need concrete slab repairs before waterproofing can go in. Construction is expected to resume in early 2027 and run to September 2027, and downtown shops stay open.

OakvilleIQ Newsroom1 source · 2 min read

Email
Aerial view of Towne Square, Oakville
Imagery: Esri, Maxar, Earthstar Geographics

Where this is

Where Towne Square is in OakvilleTowne Square, on a map of the Town of Oakville and its Official Plan communities.Towne Square
Towne SquareOutlines are the Town’s Official Plan communities.
In this story3 sections
  1. What the Town announced
  2. What crews found
  3. What happens in 2027

The details

What the Town announced

The Town of Oakville is planning to pause construction at Towne Square starting in mid-December 2026 and continuing into early 2027. In a news release on November 18, the Town said timelines may change depending on weather and construction progress, and that downtown shops and restaurants will remain open and accessible.

During the pause, all construction equipment, materials and fencing will be removed from the worksite, the Town says. Decorative hoarding and wayfinding signage will also come down, which the release describes as creating a more open environment for the holiday season. Before the pause, temporary asphalt will be installed in completed areas so the square stays safe and accessible, including for people attending Downtown Oakville BIA events.

What crews found

The release says construction began on September 30, 2026 and that crews have made steady progress on key infrastructure improvements. It also says they encountered unexpected conditions that require concrete slab repairs to walkways and to areas in front of businesses, and that this work must be done before the waterproofing can be installed.

The Town says it is working with its contractor and business tenants to keep the project on schedule. The release does not give a cost for the slab repairs or say how long they will take.

What happens in 2027

Construction is expected to resume in early 2027, weather permitting, and continue through to September 2027. During that time the Towne Square lawn will be closed to the public. The Town says a portion of George Street, between Lakeshore Road East and Church Street, will be closed until the end of construction to accommodate Downtown Oakville BIA and other downtown events and activities. Access to the CIBC parking lot and Municipal Lot 3 will remain open.

Towne Square timeline, as the Town describes it
Construction began
September 30, 2026
Planned pause
Starting mid-December 2026, continuing into early 2027
During the pause
Equipment, materials, fencing, decorative hoarding and wayfinding signage removed
Work resumes
Early 2027, weather permitting
Work continues
Through to September 2027
George Street
A portion between Lakeshore Road East and Church Street closed until the end of construction

When finished, the Town says, the square will have amphitheatre-style seating, a water feature, raised planters and seating areas, new trees, an updated central lawn, decorative lighting and new accessible paving. The Millennium Tower Clock was removed and placed in storage in early September 2026 and will be returned once the project is completed.