Trail along Sixteen Mile Creek closed for slope stabilization, reopening expected fall 2026

The Town is engineering a fix for the eroding west embankment at Fourth Line and Dundas, where rock falls and downed trees have shut a section of the Heritage Trail since the slope failures began.

OakvilleIQ Newsroom1 source · 1 min read

Email

What’s next: Closes Oct 2026

Satellite view of the Sixteen Mile Creek Heritage Trail area near Fourth Line in Oakville, with the trail path marked in red
Imagery: Google, Airbus, Maxar Technologies

The details

What happened to the trail

The Sixteen Mile Creek Heritage Trail runs along the west embankment of the Sixteen Mile Creek valley. The Town of Oakville says the slope has had repeated failures, mostly in its upper section between the trail and Fourth Line. Natural erosion has sent rock and shale fragments onto the pathway, and fallen trees and vegetation have blocked it.

The Town closed the trail segment just south of Dundas Road and east of Fourth Line due to safety concerns. The closure remains in effect while remediation is designed and built.

What the Town is doing

The Town's project goal is to stabilize the slope with an engineered design and reopen the Heritage Trail. The project area covers about 1.0 hectare (2.47 acres). WSP is the consultant.

Project status
Geotechnical investigation
Complete
Slope stability assessment
Complete — the Town evaluated retaining walls, retained soil systems and regrading, and selected a preferred option
Environmental fieldwork
Complete — ecological land classification, vegetation surveys, Species at Risk surveys and habitat screening
Tree inventory
Complete
Detailed design
Underway
Tendering
Targeted for end of 2025

Environmental constraints

Construction must avoid critical nesting and breeding periods for sensitive local species, per Ministry of Natural Resources and Forestry and Conservation Halton requirements. The project also requires environmental permits and approvals under the Conservation Authorities Act and the Endangered Species Act.

Timeline

The Town's project page targets completion by fall 2026. The tendering step was targeted for the end of 2025. The page does not state a construction start date.

Key details
Location
Fourth Line and Dundas Street West, Ward 4
Project area
About 1.0 hectare (2.47 acres)
Consultant
WSP
Completion target
Fall 2026
Contact
ServiceOakville: 905-845-6601 or service@oakville.ca

Sources

Every factual claim above traces to one of these documents.

  1. Town of Oakville

    Sixteen Mile Creek Heritage Trail Slope Remediation

    Retrieved October 17, 2026